Granisle Wastewater Treatment Plant Upgrade
Federal contribution
$2.6M
$2,623,740
Federal share60%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Granisle
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2021
- Construction end5 months earlyforecast Nov 30, 2022