Highway 16 Resurfacing

Smithers, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.3M
$1,250,057
Federal share50%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Jul 22, 2010(actual)
Construction end
Oct 2, 2010(actual)