Smithers - Wastewater Treatment Plant Upgrade

Smithers, British Columbia

approvedWastewaterGIS
Federal contribution
$3.1M
$3,052,584
Federal share40%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2024
today
2024202520262027
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Smithers
Construction start
Jul 6, 2026(forecast)
Construction end
Aug 20, 2027(forecast)

Also in Smithers

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66926 in the federal list. How to read these figures.