Back to projects

Highway 97 Resurfacing

Penticton, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,050,000
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Apr 1, 2010(actual)
Construction end
Aug 13, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 30, 2010
  • Construction end6 weeks lateforecast Jun 30, 2010

Also in Penticton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37349 in the federal list. How to read these figures.