Highway 3 Resurfacing
Federal contribution
$1.3M
$1,319,000
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jul 27, 2010(actual)
- Construction end
- Oct 22, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 30, 2010
- Construction end2 weeks lateforecast Oct 8, 2010
Also in Princeton
- Highway 3 - Sunday Summit and Sunday Creek$6.4M
- Princeton - Well #4 Upgrades for Climate Change$2.6M
- BC Hydro - Customer Connection Project: Copper Mountain Mine Trolley Assist$2.5M
- Okanagan-Similkameen - Missezula Lake Water System Upgrades$916.1K
- Princeton - Water System Extension to East Princeton$863.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37350 in the federal list. How to read these figures.