Princeton - Well #4 Upgrades for Climate Change

Princeton, British Columbia

underwayDisaster MitigationGIS
Federal contribution
$2.6M
$2,583,200
Federal share40%

of $6.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2024
today
20242025202620272028
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Princeton
Construction start
Sep 9, 2024(actual)
Construction end
Apr 30, 2028(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2024

Also in Princeton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67759 in the federal list. How to read these figures.