Back to projects

Highway 1 Resurfacing - North of Yale

Yale, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.7M
$1,678,499
Federal share50%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 26, 2010(actual)
Construction end
Aug 26, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 6, 2010
  • Construction end6 weeks lateforecast Jul 15, 2010

Also in Yale