Highway 1 Resurfacing - North of Yale
Federal contribution
$1.7M
$1,678,499
Federal share50%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- May 26, 2010(actual)
- Construction end
- Aug 26, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 6, 2010
- Construction end6 weeks lateforecast Jul 15, 2010
Also in Yale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37366 in the federal list. How to read these figures.