Fraser Valley - Regional District Electoral Area B - Yale Community Park
Federal contribution
$164,741
Federal share80%
of $205.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2021
20222023202420252026
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Regional District of Fraser Valley
- Construction start
- Jul 2, 2021(actual)
- Construction end
- Feb 26, 2026(forecast)
Against the original forecast
- Construction start2.2 years earlyforecast Sep 5, 2023
Also in Yale