Renovating and Upgrading the Alyne-Lebel Centre
Federal contribution
$833,300
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2010
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Groupe de ressources techniques en arts (GRT-ARTS)
- Construction start
- Aug 19, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 26, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 38862 in the federal list. How to read these figures.