Pavement Reconstruction on route 138 in Port-Cartier

Port-Cartier, Quebec

completeHighways and RoadsISF
Federal contribution
$611,033
Federal share34%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
2011
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 6, 2011(actual)
Construction end
Jul 8, 2011(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Jul 30, 2011

Also in Port-Cartier

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 38920 in the federal list. How to read these figures.