Wearing Course on Route 138 in the Municipality of Port-Cartier
Federal contribution
$1.7M
$1,656,305
Federal share41%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 12 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Nov 19, 2010(actual)
- Construction end
- Jul 21, 2011(actual)
Against the original forecast
- Construction start7 months earlyforecast Jun 13, 2011
Also in Port-Cartier
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40755 in the federal list. How to read these figures.