Pavement Reconstruction on Route 138 in Port-Cartier and Baie-Trinité
Federal contribution
$694,329
Federal share36%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Oct 1, 2010(actual)
- Construction end
- Nov 15, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2010
- Construction end2 weeks lateforecast Oct 29, 2010
Also in Baie-Trinité