Pavement Reconstruction on route 138 in Baie-Trinité
Federal contribution
$2.5M
$2,452,910
Federal share46%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
2011
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 8, 2010(actual)
- Construction end
- Jul 8, 2011(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Sep 15, 2010
- Construction end8 weeks earlyforecast Aug 30, 2011