Construction of indoor soccer center near St-Michel environmental complex
Federal contribution
$6.3M
$6,340,200
Federal share33%
of $19.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
201020112012201320142015
Built
Approved 3 months after the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Montréal
- Construction start
- Jan 6, 2011(actual)
- Construction end
- Dec 15, 2014(actual)
Against the original forecast
- Construction start9 months lateforecast Apr 1, 2010
- Construction end3 years lateforecast Dec 31, 2011
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 38943 in the federal list. How to read these figures.