Fraser Richmond - North Access Road Services Extension

Richmond, British Columbia

completeWastewaterISF
Federal contribution
$520,500
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 23, 2009
ApprovedJan 29, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Dec 16, 2009(actual)
Construction end
Jul 10, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 15, 2009
  • Construction end6 months earlyforecast Dec 31, 2010

Also in Richmond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39040 in the federal list. How to read these figures.