Back to projects

Maple Ridge Sewer Extension

Maple Ridge, British Columbia

completeWastewaterISF
Federal contribution
$3.0M
$3,000,000
Federal share33%

of $9.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedNov 19, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 10, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 26, 2010

Also in Maple Ridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39139 in the federal list. How to read these figures.