225 Street Pump Station and Force Main Upgrade - Phase 1

Maple Ridge, British Columbia

completeWastewaterCWWF
Federal contribution
$601,750
Federal share50%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2017201920212023
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Maple Ridge
Construction start
May 1, 2016(actual)
Construction end
Oct 6, 2022(actual)

Against the original forecast

  • Construction start2.7 years earlyforecast Jan 7, 2019
  • Construction end6 months earlyforecast Mar 31, 2023