225 Street Pump Station and Force Main Upgrade - Phase 1
Federal contribution
$601,750
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2017201920212023
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Maple Ridge
- Construction start
- May 1, 2016(actual)
- Construction end
- Oct 6, 2022(actual)
Against the original forecast
- Construction start2.7 years earlyforecast Jan 7, 2019
- Construction end6 months earlyforecast Mar 31, 2023
Also in Maple Ridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49884 in the federal list. How to read these figures.