Charlevoix Museum Upgrades

La Malbaie, Quebec

completeCultureISF
Federal contribution
$204,204
Federal share26%

of $780.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2010
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Musée de Charlevoix
Construction start
Nov 22, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 18, 2010