Kakisa Local Roads Development
Federal contribution
$125,000
Federal share50%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 18, 2010
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Kakisa, Designated Authority
- Construction start
- Sep 16, 2010(actual)
- Construction end
- Oct 14, 2010(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Nov 30, 2010
Also in Kakisa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39188 in the federal list. How to read these figures.