Kakisa Community Drainage Improvements and Road Upgrades

Kakisa, Northwest Territories

underwayHighways and RoadsRNIS
Federal contribution
$282,433
Federal share75%

of $376.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2021
today
2022202420262028
BuiltForecast

Approved 2 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Ka’a'gee Tu First Nation
Construction start
May 1, 2022(actual)
Construction end
Oct 31, 2028(forecast)

Against the original forecast

  • Construction start9 months lateforecast Aug 1, 2021

Also in Kakisa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60249 in the federal list. How to read these figures.