Rehabilitation of Highway 39
Federal contribution
$2.1M
$2,125,000
Federal share50%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- May 27, 2010(actual)
- Construction end
- Jul 15, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2010
- Construction end4 weeks lateforecast Jun 18, 2010
Also in Regina
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39253 in the federal list. How to read these figures.