Program for the renewal of drinking water and wastewater pipes
Federal contribution
$276,331
Federal share31%
of $891.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 8, 2010
20102011
Built
Approved 8 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Chambly
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Also in Chambly
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39287 in the federal list. How to read these figures.