Back to projects

Securing the electrical entrance and the emergency network

Chambly, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$321,158
Federal share80%

of $401.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 11, 2022(actual)
Construction end
Nov 29, 2023(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 1, 2022
  • Construction end3 months lateforecast Aug 30, 2023

Also in Chambly