Biomethanation and composting project in Montreal
Federal contribution
$33.1M
$33,096,005
Federal share25%
of $130.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedFeb 1, 2010
ApprovedMar 10, 2017
20102014201820222026
BuiltForecast
Approved 7.1 years after the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- City of Montréal
- Construction start
- Jul 14, 2019(actual)
- Construction end
- Mar 25, 2026(forecast)
Against the original forecast
- Construction start2 months lateforecast May 15, 2019