Guild Hall Facility Upgrades
Federal contribution
$324,000
Federal share50%
of $648.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 19, 2010
20102011
Built
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- May 17, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 17, 2010
- Construction end3 months lateforecast Jan 11, 2011
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39343 in the federal list. How to read these figures.