Guild Hall Facility Upgrades

Whitehorse, Yukon

completeCultureISF
Federal contribution
$324,000
Federal share50%

of $648.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 19, 2010
20102011
Built

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Yukon
Construction start
May 17, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 17, 2010
  • Construction end3 months lateforecast Jan 11, 2011

Also in Whitehorse

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39343 in the federal list. How to read these figures.