Highway 11 - Mission Bridge Railing Improvement

Mission, British Columbia

completeHighways and RoadsISF
Federal contribution
$562,255
Federal share42%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 19, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Jul 6, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 23, 2010

Also in Mission

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39403 in the federal list. How to read these figures.