City of Mission 7th Avenue Greenway

Mission, British Columbia

completeActive TransportationATF
Federal contribution
$1.4M
$1,351,848
Federal share57%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2022
20232024
Built

Approved 5 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
City of Mission
Construction start
Jan 3, 2023(actual)
Construction end
Sep 18, 2024(actual)

Against the original forecast

  • Construction start7 months lateforecast Jun 1, 2022
  • Construction end23 months lateforecast Nov 1, 2022

Also in Mission

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64300 in the federal list. How to read these figures.