Hatzic - Construction of Hatzic Pump Station
Federal contribution
$1.3M
$1,251,649
Federal share31%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 24, 2012
2012201320142015
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Dewdney Area Improvement District
- Construction start
- Jan 1, 2013(actual)
- Construction end
- Mar 31, 2015(actual)