Renovation of Yonge Street Mission Infrastructure
Federal contribution
$456,971
Federal share49%
of $930.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 2, 2010
2011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Yonge Street Mission
- Construction start
- Apr 12, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end5 months lateforecast May 31, 2011