Upgrades to the McCarthy Pump Station
Federal contribution
$2.1M
$2,133,333
Federal share33%
of $6.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
2011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Regina
- Construction start
- Jun 8, 2010(actual)
- Construction end
- Oct 14, 2011(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 31, 2011
Also in Regina
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39461 in the federal list. How to read these figures.