Greystone Gravel Lanes Rehabilitation
Federal contribution
$39,667
Federal share33%
of $119.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Sep 15, 2010(actual)
- Construction end
- Nov 15, 2010(actual)
Against the original forecast
- Construction end2 weeks lateforecast Oct 31, 2010
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39498 in the federal list. How to read these figures.