Highway 21 - Battle River Bridge

Camrose, Alberta

completeHighways and RoadsISF
Federal contribution
$153,047
Federal share48%

of $316.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 15, 2010(actual)
Construction end
Sep 24, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 5, 2010
  • Construction end6 months earlyforecast Mar 31, 2011

Also in Camrose

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39554 in the federal list. How to read these figures.