Highway 616 Roadwork
Federal contribution
$2.0M
$1,964,788
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jun 25, 2010(actual)
- Construction end
- Nov 27, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2011
Also in Camrose
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39571 in the federal list. How to read these figures.