Back to projects

Development of Vincennes recreational tourism park

Beaumont, Quebec

completeRecreationCC Top Up
Federal contribution
$413,018
Federal share25%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2010
2011
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Municipality of Beaumont
Construction start
Oct 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2010

Also in Beaumont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39582 in the federal list. How to read these figures.