Back to projects

Construction of a recreational pavilion at the park and tourist destination Vincennes in Beaumont

Beaumont, Quebec

completeRecreationSCF
Federal contribution
$118,076
Federal share33%

of $354.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
201720182019
Built

Approved 6 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Beaumont
Construction start
Nov 24, 2017(actual)
Construction end
Oct 21, 2019(actual)

Against the original forecast

  • Construction start7 months lateforecast May 2, 2017
  • Construction end2.3 years lateforecast Jun 24, 2017