Science North Infrastructure Renewal
Federal contribution
$2.3M
$2,295,431
Federal share50%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 12, 2010
ApprovedMar 24, 2011
2011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Mar 12, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jan 31, 2010