Highway repairs between Saint-Paulin and Saint-Élie-de-Caxton

Saint-Paulin, Quebec

completeHighways and RoadsCC Top Up
Federal contribution
$637,799
Federal share31%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2010
2011
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 19, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Sep 6, 2010

Also in Saint-Paulin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39632 in the federal list. How to read these figures.