Back to projects

Sanitation in the Lac Bergeron

Saint-Paulin, Quebec

completeDrinking WaterCWWF
Federal contribution
$344,998
Federal share29%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 6, 2018(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2018
  • Construction end8 weeks lateforecast Dec 31, 2018

Also in Saint-Paulin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48829 in the federal list. How to read these figures.