Repairs to Route 232 in Saint-Michel-du-Squatec

Saint-Michel-du-Squatec, Quebec

completeHighways and RoadsISF
Federal contribution
$444,377
Federal share44%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 28, 2010(actual)
Construction end
Sep 15, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2010
  • Construction end6 weeks earlyforecast Oct 30, 2010

Also in Saint-Michel-du-Squatec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39637 in the federal list. How to read these figures.