Treatment Upgrades to Drinking Water System
Saint-Michel-du-Squatec, Quebec
Federal contribution
$411,478
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Saint-Michel-du-Squatec
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Dec 16, 2022(actual)
Against the original forecast
- Construction end5 months lateforecast Jul 31, 2022
Also in Saint-Michel-du-Squatec