Treatment Upgrades to Drinking Water System

Saint-Michel-du-Squatec, Quebec

completeDrinking WaterGIS
Federal contribution
$411,478
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Saint-Michel-du-Squatec
Construction start
Jun 1, 2021(actual)
Construction end
Dec 16, 2022(actual)

Against the original forecast

  • Construction end5 months lateforecast Jul 31, 2022

Also in Saint-Michel-du-Squatec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56703 in the federal list. How to read these figures.