Highway 400 - St. Vincent Bridge Rehabilitation
Federal contribution
$1.2M
$1,230,879
Federal share41%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Apr 21, 2010(actual)
- Construction end
- Sep 13, 2011(actual)
Against the original forecast
- Construction end6 weeks lateforecast Aug 5, 2011
Also in Barrie
- Allandale Mobility Hub & Downtown Connection Hub - Construction$9.9M
- Conventional Fleet Replacement$9.4M
- HVAC upgrades for schools and portables; Purchase of new portables; Window replacement$8.0M
- Sanitary Servicing to Reduce Phosphorus to Lake Simcoe- Royal Oak, Bay, Cottage Lane$5.3M
- Construction of a New Fire and Emergency Services Station and Headquarters$4.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39641 in the federal list. How to read these figures.