Renewal of the Killarney Residential Ontario Ranger Camp
Federal contribution
$437,863
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Sep 21, 2010(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 1, 2010
- Construction end3 weeks earlyforecast Jul 22, 2011
Also in Killarney
- Rehabilitation and Realignment of Hartley Bay Road$1.3M
- Killarney Landfill Leachate Collection and Treatment System$276.5K
- Expansion of the Killarney Waste Disposal Site$153.0K
- Killarney Water Treatment Plant Infrastructure Repairs$115.1K
- Conduct a survey and inspection of the Sewage Collection System to develop a work plan/tender package for required upgrades/repairs.$61.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39643 in the federal list. How to read these figures.