Renewal of the Killarney Residential Ontario Ranger Camp

Killarney, Ontario

completeRecreationISF
Federal contribution
$437,863
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Sep 21, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 1, 2010
  • Construction end3 weeks earlyforecast Jul 22, 2011

Also in Killarney

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39643 in the federal list. How to read these figures.