Back to projects

Conduct a survey and inspection of the Sewage Collection System to develop a work plan/tender package for required upgrades/repairs.

Killarney, Ontario

completeWastewaterCWWF
Federal contribution
$61,904
Federal share50%

of $123.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Killarney
Construction start
Dec 1, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast May 15, 2017
  • Construction end4 weeks lateforecast Oct 31, 2018