Conduct a survey and inspection of the Sewage Collection System to develop a work plan/tender package for required upgrades/repairs.
Federal contribution
$61,904
Federal share50%
of $123.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Killarney
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start7 months lateforecast May 15, 2017
- Construction end4 weeks lateforecast Oct 31, 2018
Also in Killarney