Highway 400 - Innisfil Creek Bridge Rehabilitation
Federal contribution
$250,000
Federal share50%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Sep 9, 2010(actual)
- Construction end
- Oct 15, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2010
- Construction end2 months lateforecast Aug 3, 2011
Also in Barrie
- Allandale Mobility Hub & Downtown Connection Hub - Construction$9.9M
- Conventional Fleet Replacement$9.4M
- HVAC upgrades for schools and portables; Purchase of new portables; Window replacement$8.0M
- Sanitary Servicing to Reduce Phosphorus to Lake Simcoe- Royal Oak, Bay, Cottage Lane$5.3M
- Construction of a New Fire and Emergency Services Station and Headquarters$4.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39654 in the federal list. How to read these figures.