Highway 401 - Farewell Creek bridge Rehabilitation
Federal contribution
$198,736
Federal share40%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Feb 16, 2011(actual)
- Construction end
- Sep 15, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jan 26, 2011
- Construction end2 weeks earlyforecast Sep 30, 2011
Also in Oshawa
- Oshawa Civic Complex Renewal and Expansion$6.2M
- WIFI Access Points; Window replacement; HVAC Upgrades; Bottle Water Filling Stations; Sink replacements$5.6M
- Harmony Creek Trail extension in Oshawa ON$1.5M
- Storm Water Management Pond Cleaning by removal and disposal of sediment at 10 locations.$582.2K
- Gym Partition; Accessible door operators; Expand shared kindergarten and childcare outdoor space$312.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39660 in the federal list. How to read these figures.