Awenda Park Infrastructure Upgrade

Penetanguishene, Ontario

completeRecreationISF
Federal contribution
$72,949
Federal share49%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Aug 11, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Sep 1, 2010
  • Construction end3 months lateforecast Dec 15, 2010

Also in Penetanguishene

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39715 in the federal list. How to read these figures.