Back to projects

Development of an urban park in the district along Sabourin Street

Ville-Marie, Quebec

completeRecreationCC Top Up
Federal contribution
$28,122
Federal share33%

of $84.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2010
2011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Ville-Marie
Construction start
Apr 1, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 months earlyforecast Aug 3, 2010
  • Construction end6 months lateforecast Sep 25, 2010

Also in Ville-Marie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39736 in the federal list. How to read these figures.