Back to projects

Development of Parc des Clubs

Ville-Marie, Quebec

approvedRecreationCCRIS
Federal contribution
$1.1M
$1,098,276
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 19, 2022
today
2022202420262028
BuiltForecast

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Ville-Marie
Construction start
Oct 19, 2023(forecast)
Construction end
May 27, 2028(forecast)

Also in Ville-Marie