Rehabilitating and Repaving Route 2

Moncton, New Brunswick

completeHighways and RoadsISF
Federal contribution
$170,000
Federal share50%

of $340.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 30, 2010
ApprovedJul 28, 2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
May 12, 2010(actual)
Construction end
Jul 26, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 15, 2010
  • Construction end3 weeks earlyforecast Aug 14, 2010

Also in Moncton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39751 in the federal list. How to read these figures.