Highway 14 - Passing Lanes Construction
Federal contribution
$402,500
Federal share50%
of $805.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
2011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- May 29, 2011(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 15, 2011
Also in Strathcona County
- Strathcona County Transit Double Decker Buses, Fleet Refurbishment, and Cutaway Buses$4.0M
- Strathcona County Transit Regular Passenger Buses$2.6M
- Strathcona County Transit Fleet Replacement$1.8M
- Strathcona County Emerald Hills Leisure Centre Expansion Development$1.4M
- Strathcona County Millennium Place Recreation Centre - Main Floor Flooring Replacement$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39769 in the federal list. How to read these figures.